South Korea Lifts Honam Grid Restrictions, Boosts Solar Capacity — Eter News

Enriched Analysis 深度解析

South Korea Lifts Honam Grid Restrictions, Boosts Solar Capacity韩国解除湖南地区电网接入限制,提升太阳能装机容量

South Korea's Ministry of Climate, Energy and Environment has removed grid connection restrictions in the Honam region, introduced flexible connection rules, and plans to use energy storage instead of new lines. The measures are projected to raise national transmission-level renewable hosting capacity from 119 GW to 171 GW by 2030.韩国气候能源环境部解除湖南地区的电网接入限制,引入柔性接入规则,并计划以储能替代新建线路。预计到2030年,全国输电级可再生能源承载容量将从119吉瓦提升至171吉瓦。

IndexBox 1 Oct 2026 2026年10月1日

1616

Distribution line solar ceiling配电线路太阳能上限

33

Solar via distribution storage by 20302030年前经配电储能接入的太阳能

99

Connection rights clawed back已回收的并网权

01The Story新闻事实

South Korea's Ministry of Climate, Energy and Environment has removed grid connection restrictions in the Honam region, introduced flexible connection rules, and plans to use energy storage instead of new lines. The measures are projected to raise national transmission-level renewable hosting capacity from 119 GW to 171 GW by 2030.韩国气候能源环境部解除湖南地区的电网接入限制,引入柔性接入规则,并计划以储能替代新建线路。预计到2030年,全国输电级可再生能源承载容量将从119吉瓦提升至171吉瓦。

  • The MCEE removed barriers to new renewable energy hookups in Honam, covering Gwangju and North and South Jeolla provinces.气候能源环境部解除了湖南地区(含光州及全罗北道、全罗南道)新增可再生能源并网的障碍。
  • Flexible connections raise the solar ceiling on a distribution line from 14 MW to 16 MW and at a substation from 50 MW to 60 MW, enabling an extra 2.6 GW of solar in Honam without new grid infrastructure.柔性接入将配电线路太阳能上限从14兆瓦提高至16兆瓦,变电站上限从50兆瓦提高至60兆瓦,无需新建电网即可在湖南地区新增2.6吉瓦太阳能。
  • The ministry has clawed back 9 GW of grid connection rights from non-viable solar projects and expects to recover over 10 GW in Honam alone by 2030.该部已从不可行的太阳能项目中收回9吉瓦并网权,预计到2030年仅湖南地区即可回收超过10吉瓦。
  • The Korea Power Exchange launched a tender on Sept. 22 for 1,100 MW/6,600 MWh of six-hour battery storage under 15-year contracts, with winners named in November.韩国电力交易所于9月22日启动1,100兆瓦/6,600兆瓦时六小时储能电池招标,合同期15年,中标者预计11月公布。
  • The Export-Import Bank of Korea projects South Korea will add 3.5 GW of solar this year.韩国输出入银行预计韩国今年将新增3.5吉瓦太阳能装机。

By combining flexible connections, storage deployment, and reallocation of idle grid rights, South Korea aims to unlock tens of gigawatts of renewable capacity without major new transmission build-out.通过柔性接入、储能部署和回收闲置并网权的组合措施,韩国力图在不大规模新建输电设施的情况下释放数十吉瓦的可再生能源容量。

024 Dimensions维度分析

Cause因果关系

Capacity gains from flexible connections柔性接入带来的容量提升

Allowing projects to connect beyond standard hosting limits, with output curtailed when needed, immediately raises usable grid capacity.允许项目在超出标准承载极限的情况下并网、必要时削减出力,可立即提高可用电网容量。

Distribution line solar ceiling配电线路太阳能上限

Distribution line solar ceiling配电线路太阳能上限16 MW

Substation solar ceiling变电站太阳能上限60 MW

Extra solar enabled in Honam湖南地区新增太阳能2.6 GW

  • Projects already in the connection queue get precedence; newcomers file under updated rules from January 2027.已在并网队列中的项目享有优先权;新项目自2027年1月起按新规则申请。
Future signal前瞻信号

Storage instead of new lines以储能替代新建线路

The ministry targets 3 GW of extra solar in saturated zones via distribution-level storage and 1.6 GW via substation storage by 2030, without disclosing required battery capacity.该部目标到2030年通过配电网储能接入3吉瓦饱和区域新增太阳能,并通过变电站储能再接入1.6吉瓦,但未披露所需电池容量。

Solar via distribution storage by 20302030年前经配电储能接入的太阳能

3 GW3吉瓦

Solar via substation storage by 20302030年前经变电站储能接入的太阳能

1.6 GW1.6吉瓦

  • The Korea Power Exchange tendered 1,100 MW/6,600 MWh of six-hour battery storage with commissioning slated by February 2029.韩国电力交易所招标1,100兆瓦/6,600兆瓦时六小时储能电池,计划2029年2月前投运。
Consequence影响推演

Reclaiming idle grid rights回收闲置并网权

Scrutiny of stalled projects has already recovered 9 GW of connection rights, with over 10 GW expected in Honam by 2030; future allocation will use a 67.2% on-time completion rate assumption.对停滞项目的审查已回收9吉瓦并网权,预计到2030年湖南地区将超过10吉瓦;未来分配将按67.2%的按时完工率假设进行。

Connection rights clawed back已回收的并网权

9 GW9吉瓦

Expected recovery in Honam by 20302030年前湖南地区预期回收量

10 GW10吉瓦

Assumed on-time completion rate假设的按时完工率

67.2 %67.2%

  • From January 2027, connection rights will be awarded via competitive bidding under a revamped renewable portfolio standard rather than first-come, first-served.自2027年1月起,并网权将通过修订后的可再生能源配额制下的竞争性招标授予,而非先到先得。
Comparison对比

Projected national capacity gains全国容量提升预测

Revised connection studies assuming renewables dispatch first are estimated to unlock 20 GW of additional renewable capacity nationwide by 2030, lifting hosting capacity substantially.修订后的并网研究假设可再生能源优先调度,预计到2030年可在全国释放20吉瓦新增可再生能源容量,大幅提升承载容量。

Transmission-level hosting capacity by 20302030年输电级承载容量

Transmission-level hosting capacity by 20302030年输电级承载容量171 GW

Distribution-level capacity by 20302030年配电级容量110 GW

Honam transmission capacity by 20302030年湖南输电容量64 GW

Honam distribution capacity by 20302030年湖南配电容量30 GW

  • East coast restrictions are scheduled to end in the first half of 2027 with completion of the first phase of an HVDC link to Singapyeong.东海岸限制计划于2027年上半年随至新平 HVDC 线路一期完工而解除。

03Timeline时间线

  1. 2026-06 Solutions for Our Climate paper criticized the first-come, first-served queue for letting stalled projects tie up grid capacity.气候解决方案智库论文批评先到先得机制使停滞项目占用电网容量。
  2. 2026-09-22 Korea Power Exchange launched tender for 1,100 MW/6,600 MWh of battery storage.韩国电力交易所启动1,100兆瓦/6,600兆瓦时储能电池招标。
  3. 2026-10-01 MCEE announced removal of Honam grid connection restrictions.气候能源环境部宣布解除湖南地区并网限制。
  4. 2027-01 New connection rules and competitive bidding under revamped RPS take effect.新并网规则及修订后配额制下的竞争性招标生效。
  5. 2027-06 East coast restrictions scheduled to end with first phase of HVDC link to Singapyeong.东海岸限制计划随至新平HVDC线路一期完工而解除。

Key takeaway核心结论

South Korea's grid reform package uses flexible connections, storage, and rights reallocation to expand renewable hosting capacity from 119 GW to 171 GW by 2030 without major new line construction.韩国电网改革方案通过柔性接入、储能和并网权再分配,到2030年将可再生能源承载容量从119吉瓦提升至171吉瓦,而无需大规模新建线路。

04What to Watch后续关注

  1. Winners of the November battery storage tender and progress toward February 2029 commissioning.11月储能招标的中标结果及2029年2月投运目标的进展。
  2. Implementation of the new connection rules and competitive bidding starting January 2027.2027年1月起的新并网规则和竞争性招标的落实情况。
  3. Ending of east coast restrictions in the first half of 2027 alongside the HVDC link's first phase.2027年上半年东海岸限制解除及HVDC线路一期进展。
  4. Whether the projected 20 GW of unlocked renewable capacity materializes in Yeongnam and Gangwon.预计释放的20吉瓦可再生能源容量能否在岭南和江原地区落地。

05Uncertainties不确定因素

  • The ministry did not disclose how much battery capacity the storage-based connection plan would require.该部未披露基于储能的并网计划所需电池容量。
  • Actual curtailment impacts of flexible connections on project economics are not quantified in the source.柔性接入对项目经济性的实际弃电影响在源文中未量化。